How to track construction submittals (free construction submittal log template)

This guide is written by the team behind WorkHoist, which sells construction software — read it with that in mind. The template is free, needs no email address and works without WorkHoist. The last section says where WorkHoist helps.

Last updated

The short answer

A submittal is the shop drawings, product data, samples or other information you send the architect or engineer to show that what you will build or install meets the contract. A submittal log is the list of every submittal the specs ask for, with its spec section, type, who prepares it, who reviews it, when it must be sent, when it is due back, what the reviewer decided, and whose court the ball is in. Build it from the specs before work starts, work each send-by date back from the date the item is needed on site, and do not order or install anything until its submittal is approved. The free Excel template below works out the dates, keeps the revisions together and flags what is late.

Download the construction submittal log template

Download the construction submittal log template (Excel, .xlsx). No sign-up and no email. It opens in Excel and in Google Sheets: in Google Drive choose New, then File upload, then open the file with Google Sheets.

One file per job, with these tabs:

  • Submittal Log — the register: one row per submittal with its spec section, type, sub or supplier, reviewer, the date it is needed on site and its lead time. It works out when each one must be sent and when it is due back, its status, whose court the ball is in, how long it has been with the reviewer and the next step. It flags anything late to send, overdue from the reviewer or sent back, and anything at risk because approval plus lead time lands after the date it is needed.
  • Transmittal — a printable cover sheet for any submittal and revision, with a place to list variations from the contract documents, your review, and the reviewer’s action.
  • Summary, Setup, Checklist and Start Here — counts by status and ball in court and everything that needs action; your job, reviewer, review time and the eleven submittal types; and how to use the file.

Blue text is what you type. Black text is a formula. Yellow cells are settings. The sample job has twelve submittals: door frames resubmitted after the anchors were wrong and now at risk of arriving late, ceiling tile samples overdue from the architect, diffusers rejected, an approved-as-noted ceiling grid waiting for its order, and lead-lined board that should have gone out four days ago. Its dates are set from today, so the flags keep showing; type your own over them.

What a submittal is

On federal jobs the definition is written down. Shop drawings are drawings submitted by the contractor, a subcontractor or a lower-tier subcontractor showing in detail how structural elements will be fabricated and assembled and how materials or equipment will be installed. The same clause counts diagrams, layouts, schematics, descriptive literature, illustrations, schedules, and performance and test data as shop drawings too. Cornell LII

The federal submittal specification sorts submittals into eleven types, from SD-01 Preconstruction Submittals, SD-02 Shop Drawings, SD-03 Product Data and SD-04 Samples through to SD-10 Operation and Maintenance Data and SD-11 Closeout Submittals. The template uses the same eleven. WBDG

Build the submittal register before work starts

The federal specification asks the contractor to prepare and maintain a submittal register as the work progresses, listing for each submittal the specification section it comes from, its type, the paragraph where the material or product is specified, and who approves it. The register is updated as submittal actions happen and kept at the site until final acceptance; on jobs that use the specification it also goes in with each invoice request and at least monthly. WBDG

Do the same on any job. Go through the specs section by section, add a row for every submittal they ask for, and give each one the date it is needed on site and its lead time.

Then work backwards. The send-by date is the date the item is needed on site, less the time to make and ship it after approval, less the review time your contract allows. Put that date on your construction schedule as well, as an activity of its own.

Sending, review and resubmittals

Review it yourself before it goes. On a federal job the contractor must coordinate shop drawings, review them for accuracy, completeness and compliance with the contract, and show its approval on them; drawings sent without that evidence may be returned for resubmission. Anything that varies from the contract documents must be described in writing, separately from the drawings, when the submittal goes in. Cornell LII

When it comes back, the reviewer’s action decides what happens next. Approved, or approved as noted, lets the work go ahead, with the notes followed. Revise and resubmit, or rejected, sends it back to you.

Resubmittals cost time. Under the federal specification a resubmittal gets the same review period as the first submission, and the contractor is responsible for the extra time that resubmittals take. Keep the number and add a letter for each one, so the history stays together: the specification turns submittal 18 into 18A. WBDG

Nothing gets ordered or built before approval

On a federal job, any work done before shop drawings are approved is at the contractor’s risk, and approval does not take away the contractor’s responsibility for errors or omissions in the drawings. Cornell LII

The federal specification also asks for submittals that need approval to be provided before the material or equipment they cover is acquired, and says payment for materials incorporated in the work will not be made if required approvals have not been obtained. WBDG

That is why lead times belong in the log. A long-lead item whose approval comes back late arrives late, however fast the supplier is. The template flags any submittal where the approval date plus the lead time lands after the date it is needed on site. When it is approved, release the order on a purchase order the same day.

Ball in court, and chasing late reviews

Every open submittal is with someone: you, the sub preparing it, or the reviewer. Ball in court says who. Go through the log every week: send what is due, chase anything past its due-back date, and when a late answer holds up work, write it in the daily report with the date.

A question a submittal raises is not a submittal. Put it in your RFI log, so it gets an answer and a date of its own.

Construction submittal checklist

These are the checks on the template’s Checklist tab.

  1. Is the register built from the specs?

    What a good answer sounds like: Every submittal each spec section asks for has a row before work starts.

  2. Does each row have a need date and a lead time?

    What a good answer sounds like: The date it must be on site, and how long it takes to make and ship after approval.

  3. Do send-by dates come from the schedule?

    What a good answer sounds like: The need date, less the lead time, less the review time the contract allows.

  4. Did you review it before it went out?

    What a good answer sounds like: Checked against the drawings, specs and other trades, and marked as reviewed.

  5. Are variations listed separately?

    What a good answer sounds like: Anything that differs from the contract documents is written out on the transmittal.

  6. Does every package have a transmittal?

    What a good answer sounds like: Number, revision, spec section, type, what it is, and when the answer is needed.

  7. Do resubmittals keep their number?

    What a good answer sounds like: Same number, next revision letter, with the changes marked.

  8. Is anything ordered before approval?

    What a good answer sounds like: Long-lead items wait for the approved or approved-as-noted stamp.

  9. Did the approved-as-noted comments reach the sub?

    What a good answer sounds like: The notes go to whoever is fabricating or installing.

  10. Are overdue reviews chased?

    What a good answer sounds like: A call or email the day an answer is late, and the delay recorded.

  11. Is the log updated as things happen?

    What a good answer sounds like: Dates sent and returned, and the reviewer’s action, entered the same day.

  12. Are closeout submittals tracked too?

    What a good answer sounds like: Operation and maintenance manuals, warranties and as-builts have rows and dates.

When a submittal spreadsheet stops being enough

The template works for one job with someone keeping it up. These are the signs it has been outgrown:

  • Nobody is sure which revision the architect has, or which one the sub is building from.
  • A long-lead item is ordered late because nobody noticed its approval came back.
  • The log, the schedule and the RFIs live in three different files that disagree.
  • You run several jobs and cannot see which reviewers are sitting on what.

At that point the submittals belong on the job itself, next to its RFIs, daily logs and schedule.

Where WorkHoist helps

WorkHoist keeps submittals on each project, numbered SUB-001 on, with a title, type (shop drawings, product data, samples, O&M manual, quality control or other), spec section, revision number, who submitted it and when, a reviewer from your team, a due date and the date it was reviewed. Statuses run draft, submitted, under review, approved, approved as noted, revise and resubmit, and rejected.

A submittal past its due date that has not been approved, approved as noted or rejected is flagged overdue, and the project shows how many are overdue. Submittals sit on the project next to its RFIs, daily logs, punch list and schedule. WorkHoist does not attach files to a submittal, so the drawings, data sheets and photos of samples go to the reviewer with your transmittal, and the submittal record tracks where they are.

Questions contractors ask

What is a submittal in construction?
A submittal is information the contractor sends the architect or engineer for review before building or installing something: shop drawings, product data, samples, test reports, certificates, manufacturer’s instructions, operation and maintenance data, or closeout documents. It shows that what will be built or installed meets the contract documents.
What is a submittal log?
A submittal log, or submittal register, lists every submittal a job’s specifications require, with its spec section, type, who prepares it, who reviews it, the dates it is sent and due back, the reviewer’s action, its revision and whose court the ball is in. It is built from the specs before work starts and updated as each submittal moves.
What is the difference between a submittal and an RFI?
A submittal shows the reviewer what you intend to build or install and asks for approval. An RFI, a request for information, asks a question about the contract documents and asks for an answer. A question that comes up while preparing a submittal should go in the RFI log, not in the submittal’s comments.
What does approved as noted mean?
Approved as noted means the reviewer accepts the submittal subject to the comments marked on it. Work can go ahead, but the comments have to be followed, so they need to reach whoever is fabricating or installing. Check your contract for exactly what each review action means on your job.
How long does submittal review take?
As long as your contract or specifications allow, often stated in calendar or working days. Under the federal submittal specification, a resubmittal gets the same review period as the first submission and the contractor is responsible for the extra time resubmittals take, so work send-by dates back from the date each item is needed on site.
Is there a free construction submittal log template?
Yes. WorkHoist’s construction submittal log template is a free Excel file, with no sign-up or email, that also opens in Google Sheets. It works out send-by and due-back dates, tracks revisions and ball in court, flags late and at-risk submittals, and prints a transmittal for any submittal.

Sources

  1. 48 CFR § 52.236-21, Specifications and Drawings for Construction (Feb 1997), paragraphs (d) to (f)
  2. UFGS 01 33 00 Submittal Procedures (USACE / NAVFAC / AFCEC, August 2018, change 4 02/21)

Every external claim on this page is linked to its source above. Each URL was opened and confirmed to carry the text cited from it on the date this page was last updated. Claims about what WorkHoist does are checked against WorkHoist’s code, not its marketing. The sample company, subs, reviewer and every date in the template are made up.